Heavy Equipment Manufacturer Spare Parts Inventory Optimization

Comprehensive spare parts inventory across 6 distribution centers for a leading heavy equipment manufacturer, achieving complete ERP reconciliation and implementing optimized min-max levels.

6
Distribution Centers
58K+
Unique SKUs
$32M
Inventory Value
99.4%
Final Accuracy
The Challenge

Critical Inventory Discrepancies Impacting Service Operations

A Fortune 500 heavy equipment manufacturer faced significant challenges with their spare parts inventory across multiple distribution centers, directly impacting their ability to service equipment in the field.

ERP System Discrepancies

Significant variances between physical inventory and ERP records causing stockouts and excess inventory

Inconsistent Identification

58,000+ SKUs with inconsistent labeling and identification across facilities

Obsolete Inventory

Unknown quantities of obsolete parts consuming valuable warehouse space and capital

Service Level Impact

Inventory inaccuracies leading to delayed equipment repairs and customer dissatisfaction

Spare parts inventory challenge
$4.8M

Annual cost of inventory inaccuracies and stockouts

Our Solution

Comprehensive Multi-Site Inventory Program

A phased approach combining physical verification, advanced tagging technology, and data optimization across all distribution centers.

Phase 1: Physical Verification

Complete wall-to-wall inventory of all 6 distribution centers using handheld RFID and barcode scanners.

  • 58,000+ SKUs physically verified
  • Location accuracy validation
  • Condition assessment

Phase 2: Asset Tagging

Implementation of dual barcode and RFID tagging system for enhanced tracking and identification.

  • Industrial-grade RFID tags
  • Durable barcode labels
  • Location bin labeling

Phase 3: ERP Reconciliation

Complete reconciliation of physical findings with ERP system data and resolution of all discrepancies.

  • Variance analysis and resolution
  • Data cleansing and standardization
  • System updates and validation

Phase 4: Optimization Analysis

Data-driven analysis to identify obsolete inventory and optimize stocking levels across the network.

  • Obsolescence identification
  • Slow-moving parts analysis
  • Demand pattern analysis

Phase 5: Min-Max Implementation

Development and implementation of optimized min-max inventory levels for all critical spare parts.

  • Statistical analysis of usage patterns
  • Lead time consideration
  • Service level optimization

Phase 6: Documentation

Comprehensive reporting and recommendations for ongoing inventory management improvements.

  • Detailed variance reports
  • Optimization recommendations
  • Best practice guidelines

Project Execution

Deployed a team of 28 experienced inventory specialists across all 6 distribution centers, completing the entire program in 9 weeks with minimal disruption to daily operations.

28
Team Members
9 Weeks
Project Duration
24/7
Operations Coverage
Results Achieved

Transformative Impact on Operations

The comprehensive inventory program delivered significant improvements in accuracy, efficiency, and cost savings.

Inventory Accuracy

Complete ERP reconciliation achieved

Before82.3%
After99.4%
+17.1%

Accuracy improvement

Cost Savings

Annual operational improvements

Obsolete inventory identified$2.8M
Excess inventory reduction$1.9M
Stockout cost reduction$1.4M
$6.1M

Total annual savings

42%

Faster Order Fulfillment

Improved location accuracy and system reliability

28%

Inventory Reduction

Optimized stocking levels across network

96%

Service Level Achievement

Consistent parts availability for field service

Project by the Numbers

Comprehensive inventory transformation across the entire distribution network

58,247

Unique SKUs Verified

312,500

Individual Parts Counted

58,247

RFID Tags Applied

14,892

Discrepancies Resolved

Multi-Site Coordination

Simultaneous operations across 6 distribution centers in 4 states, with centralized project management and quality control.

Quality Assurance

Three-tier verification process with 100% audit of high-value items and statistical sampling of remaining inventory.

On-Time Delivery

Project completed 3 days ahead of schedule despite scope expansion to include additional obsolescence analysis.